Drainage CCTV Investigation work will shortly be carried out. Works will be completed by Balfour Beatty and specialist sub-contractors Onsite & Quantum Traffic Management.
When will this work be delivered?
The work is due to take place on 02/06/2025 and be completed by 09/07/2025 (weekdays only) weather permitting. Please see below a breakdown of the locations, dates, and traffic management.
– Aqueduct Road, Aqueduct – 02/06/2025-05/06/2025, 08:00-17:00, Stop & Go
– A442 Shawbirch – 09/06/2025-18/06/2025, 09:30-15:00, Stop & Go
– A41 Woodcote – 24/06/2025-30/06/2025, 09:30-15:00, 2-way traffic lights
– B5063 Bratton – 30/06/2025-08/07/2025, 09:30-16:00, Stop & Go
– Hillside Road, Ketley Bank – 08/07/2025-09/07/2025, 08:00-17:00, Localised signing and guarding
These works are being delivered as part of the Telford & Wrekin Council’s investment programme to ‘Protect, Care and Invest to create a better borough’.
Balfour Beatty will be the lead delivering this work in partnership with the Council, for any questions or queries relating to this scheme please contact the highways hub:
TelfordHighways@balfourbeatty.com
Date published: 28/05/25.